Stored Materials: Avoid Double Counting After Installation
Reconcile stored materials as they become installed work. Follow two payment-application periods and identify duplicate value before carrying the total forward.
Estimated reading time: 8 minutes
Stored materials should remain traceable as they move into installed work. Reconcile the continuation-sheet columns before transferring the amount to the payment application.
Contractors complete the continuation sheet before transferring its summary to the payment application. Start with the supporting figures.
This exercise concerns AIA G702–1992 and G703–1992, using instructions updated in 2025. It excludes retainage calculations and other form families.
Stored materials: read the continuation-sheet columns
D means work completed through the previous application; E means work completed this period, including incorporated materials.
D carries prior D plus E, excluding F. E includes current work and incorporated stored materials. Recalculate F from new and remaining stored materials; incorporation, not payment, reduces it. G totals D, E and F.
Work through an example
Consider one fictional item with a scheduled value of $100,000. Its previous application records D of $10,000, E of $20,000 and F of $15,000. This period, $6,000 of those stored materials are installed, alongside $4,000 of other new work. No new materials enter storage. All amounts are US dollars; material values stay unchanged. Assume the stored materials qualify for this exercise, without claiming that arithmetic establishes eligibility. Exclude taxes, change orders and all other changes.
Current D is $30,000, E $10,000 and F $9,000. G is $49,000, up $4,000; installing previously stored materials adds no further value to G.
Leaving F at $15,000 instead produces G of $55,000, overstating the total by $6,000.
These figures don’t calculate payment due or predict approval. The architect reviews the application and may certify a different amount; the owner pays the contractor based on that certification.
Payment to another recipient requires specific identification on G702.
Stored materials: reconcile the earlier total first
The prior application has $10,000 in D, $20,000 in E and $15,000 in F. Its combined G is $45,000. That total describes completed work and qualifying stored materials under the exercise’s stipulated assumptions.
For the current period, the carried completed-work amount D is the prior D plus E, or $30,000. Carrying the entire prior G into D would also carry materials still separately tracked in F.
The original current E includes $6,000 installed from storage and $4,000 other new work, totaling $10,000. F falls from $15,000 to $9,000 because the $6,000 was incorporated.
Current G is therefore $30,000 + $10,000 + $9,000 = $49,000. The increase is only $4,000 because moving the same material from stored to incorporated changes its category, not its value.
Use a movement check beside the column total
The storage movement can be described as beginning stored value plus new qualifying storage minus incorporated value equals ending stored value. Here, $15,000 plus zero minus $6,000 equals $9,000.
The incorporated $6,000 appears in current completed work and leaves storage. If it enters E without leaving F, the same value appears in two places.
This movement check doesn’t determine that materials qualify for payment. Eligibility and supporting documentation are separate assumptions in the example and require the actual contract and review process.
Keep the scheduled item and period attached to every movement. A correct $6,000 installation record for another item shouldn’t be used to reduce this item’s stored value.
Stored materials: test full and zero incorporation
For an independent case, assume all $15,000 previously stored materials are incorporated in the current period, with the same $4,000 other new work and no new storage. D remains $30,000, E becomes $19,000 and F becomes zero.
G is again $49,000. The storage-to-work transfer is larger than in the original case, but the new value added beyond the earlier combined total is still only $4,000.
For another independent case with no incorporation, current E is only $4,000 and F remains $15,000. With D of $30,000, G is still $49,000.
These alternatives illustrate reclassification while holding other new value fixed. They aren’t three consecutive applications and shouldn’t be added together as separate current-period work.
Add newly stored value as a separate change
Return to the original $6,000 incorporation and $4,000 other new work. Now assume a separately documented and stipulated qualifying $5,000 of new materials enters storage during the period.
F becomes $15,000 + $5,000 − $6,000 = $14,000. D remains $30,000 and E remains $10,000, so G becomes $54,000.
The $9,000 increase over the prior $45,000 is the $4,000 other new work plus $5,000 newly stored value. The $6,000 incorporation remains a category movement within the already recognized material value.
The calculation doesn’t establish the proper valuation or eligibility of the new materials. Those inputs are expressly supplied for this arithmetic branch; actual documentation and contractual requirements still need review.
Locate two different duplication errors
The original mistake leaves F at $15,000 despite incorporating $6,000. With correct D of $30,000 and E of $10,000, G becomes $55,000, overstating the original correct $49,000 by $6,000.
A different mistake carries prior G of $45,000 into current D while using correct E of $10,000 and F of $9,000. G becomes $64,000, overstating the correct total by the prior $15,000 stored amount.
If both mistakes occur, $45,000 + $10,000 + $15,000 produces $70,000. The $21,000 overstatement combines the duplicated $15,000 carryforward and $6,000 incorporation.
Each addition is arithmetically valid from its entered numbers. The error concerns what those numbers represent. That’s why reviewing only a calculated total can’t replace tracing the column meanings.
Carry the corrected record into a new period
For a subsequent independent teaching period starting from the original correct current record, prior D is $30,000, prior E $10,000 and prior F $9,000. The next D is therefore $40,000.
Assume the remaining $9,000 is installed, $3,000 other new work occurs and $2,000 new qualifying materials enter storage. The next E is $12,000 and F is $2,000.
Next G is $54,000. Compared with the earlier correct $49,000, the increase is $5,000: $3,000 other new work plus $2,000 new storage.
Keep this next-period branch distinct from the earlier alternative with $5,000 newly stored materials. Mixing their opening balances would create a history not supported by either scenario.
Keep recognized value separate from payment due
The examples reconcile selected continuation-sheet values. They don’t calculate retainage, previous payments, the full application amount or a certified payment. The original scope deliberately excludes those separate calculations.
A payment for previously stored materials doesn’t by itself mean the materials were incorporated. Retain installation and remaining-storage evidence rather than using a bank payment as a substitute for the physical-status record.
Likewise, a worksheet subtotal isn’t architect certification or owner payment confirmation. Keep submitted, reviewed, certified and paid stages separately identified in the project file.
This article is an original explanation and fictional calculation, not an official form or reproduction. Use the actual licensed documents, instructions and qualified advisers for a real application.
Make the item record traceable
Link the prior application, scheduled item, material records, incorporation evidence and current calculation. Preserve corrections and identify what changed rather than overwriting the earlier application without explanation.
If a quantity, value or period is uncertain, leave the issue visible and seek clarification. A balancing number entered solely to match a desired payment obscures the very difference the worksheet should explain.
A useful stored materials reconciliation shows both the movement and the total. It recognizes new value once, carries completed work correctly and keeps incorporation distinct from payment and approval.
Stored materials: label any percentage derived from the total
The original current G of $49,000 is 49% of the stipulated $100,000 scheduled value. The current completed-work components D plus E total $40,000, or 40%, while F contributes another 9% as stored value.
Calling the combined 49% a measurement of physically installed progress would change its meaning. It includes the $9,000 still stored under the example’s assumptions.
Keep the numerator with any percentage you report. A percentage based on completed-plus-stored value and one based only on completed work need not match. Neither calculation independently certifies physical progress, material eligibility or a payment amount, and this original teaching calculation doesn’t reproduce another form field or replace the licensed instructions.
Finish the check
Reconcile the previous application, installation records and remaining materials for the same scheduled item and billing period.
Consult an attorney before completing or modifying forms; reproduction requires AIA's express written permission.
This is an original teaching example, not a reproduced form, invoice submission or legal or accounting advice. Keep project documents private; don’t send them to EasyLoanWorld.
For the broader payment schedule, use the construction-loan draw cash-flow exercise. To check for a different kind of duplication, review invoice and bank-payment double counting.